In the case of Davis Construction (South East) Ltd v Sanzen Investments Ltd [2021] EWHC 2216 (TCC), an employer attempted to defer enforcement proceedings in relation to an adjudicator’s decision based on the employer’s claims for damages for defective work and delay. The attempt was unsuccessful.
Background Facts
The contractor obtained an adjudicator’s award in respect of its final account relating to the construction of a housing development. The employer had not paid according to the decision, so the contractor applied to the High Court for summary judgment for enforcement.
The employer resisted the application and contended that the matter should be dismissed or adjourned pending resolution of the employer’s own counterclaim for damages amounting to some £200,000 for defective works and delay.
The employer relied on the inclusion of a new clause, 1.13 within the JCT Intermediate Contract with Contractor’s Design, which provided for a right of set-off in respect of sums recoverable as between the employer and contractor.
The employer had issued a formal letter of claim to the contractor in February 2021 in respect of its claim for damages. This pre-dated the contractor’s reference to adjudication in March 2021.
Despite this chronology, in its response to the adjudication in April 2021, the employer had not raised any issue as to the quality of the contractor's work.